Updated as of September 11, 2023
Monday (9/11): The contractor will be paving Crestview Drive. Santa Ana between Signal and Blanche will be ground today in preparation for the Wednesday paving.
Tuesday (9/12): Meadowbrook Road and Drown Ave will be ground and paved in one day. The limits for both streets are between Red Hill Road and Pleasant Ave.
Wednesday (9/13): Topa Topa between Blanche and Signal, Santa Ana between Blanche and Signal and Robin Court
This week will also conclude the curb ramp work. This week will include cleanup of the areas where the project work has taken place.